Construction education
An RFI — Request for Information — is the formal way a contractor asks the engineer, architect, or owner to clarify something before the crew digs in and gets it wrong.
Construction drawings and specifications are never perfect. Conditions in the field don't always match what the designer assumed. When a question comes up — a detail that's missing, a dimension that doesn't add up, a spec that conflicts with another — the contractor submits an RFI to get a written answer before proceeding.
The RFI creates a paper trail. If the answer changes the work, costs money, or affects the schedule, the RFI is the starting point for the change order claim. Without the documented question and answer, it's your word against the engineer's.
Each RFI is pinned to the specific location where the field question arose. The pin carries the description, attached plan sheets and photos, the date submitted, and the current status. You can see at a glance which parts of the project have open RFIs, which are overdue for a response, and whether any cluster in one zone — which often signals a plan conflict in that area.
RFI stands for Request for Information. It is a formal document used on construction projects to clarify something in the plans, specs, or contract before or during the work.
Typically the general contractor or subcontractor submits an RFI to the engineer, architect, or owner. Inspectors and project managers may also initiate RFIs when field conditions don't match the drawings.
It depends on the contract and the complexity of the question. Most contracts specify a response window of 7 to 14 calendar days, but critical-path RFIs can take longer and cause schedule impacts while you wait.
Unanswered RFIs can stop work, delay procurement, create conflicts between trades, and set up change order disputes. Documenting the submission date and the delay is critical for protecting your schedule and cost claims.
No, but an RFI can lead to a change order. An RFI is a question. If the answer changes the scope, cost, or schedule, a change order typically follows.